Figure 3-10 Needle valves
(1) Low-pressure needle valve (2) Liquid pipe needle valve (3) Discharge pipe needle
valve
----End
3.4 Removing the Transport Fixing Sheet Metals
3.4.1 Removing the Transport Fasteners from Floats
Context
The water tank is right under the evaporator and the
oats (also called liquid level
switches) are on the right side of the water tank, as shown in Figure 3-11.