NO TE
For scenarios where a container is transported without refrigerant, keep 0.3 to 0.4 MPa of
nitrogen in the pipe.
----End
3.10 Installing Cabinet Accessories
To expand an indoor unit to 1200 mm deep, install an enclosure frame. To expand
an indoor unit to 2200 mm high, install an top frame.
3.10.1 (Optional) Installing an Enclosure Frame
Procedure
Step 1 Open the front door. Remove the power cable of the display screen and the
ground cable for the front door. Then pull the front door upwards and remove it.
Step 2 Remove one bolt
xing plate, two connection plates, and two hinges.
Step 3 Move the enclosure frame to the front door, and adjust the anchor bolts of the
enclosure frame to ensure that the enclosure frame has the same height with the
cabinet.
Step 4 Secure the enclosure frame to the front door using eight M5 screws, as shown in
Figure 3-34.
NetCol5000-A(025, 035) In-row Air Cooled Smart
Cooling Product
User Manual (600 mm Width) 3 Installation Guide
Issue 17 (2020-10-22) Copyright © Huawei Technologies Co., Ltd. 63