2-46 • Installing BSC hardware 8018653 1.1
12. Type 1, then press [Return] to select Switched In.
13. Set module front panel DIP switches to the SUDs setting shown
in figure 2-29.
14. Release the front panel reset switch toggle so that it returns to
the center position. Verify that the status LED readout displays
a P after completing SUDs, then displays a d.
Note
If the status readout does not display a P, the
module has failed SUDs. Refer to section 4,
“Troubleshooting.”
Repeat steps 1 through 14 (if required) to install CPMs into the remain-
ing CCP slots (slots 6, 7, and 8), then refer to section “Installing CAP
modules.”
Installing CPMs in CAP slots
1. Remove a CPM (see table 2-1) from its shipping container.
Save the container.
2. Press the front panel reset switch toggle into the down position.
3. Install the module into slot 9 (bottom) of the card cage.
4. Use a crosstip screwdriver to tighten the module’s captive
screws.
5. Set module front panel DIP switches to the SUDs setting shown
in figure 2-29.
6. Release the front panel reset switch toggle so that it returns to
the center position. Verify that the status LED readout displays
a P after completing SUDs, then displays a d.
Note
If the status readout does not display a P, the
module has failed SUDs. Refer to section 4,
“Troubleshooting.”
Repeat steps 1 through 6 (if required) to install CPMs into the remaining
CAP slots (slots 10, 11, 12, and 13), then refer to section “Installing
switching transcoder modules.”