Chapter 12. RAS, monitoring, and troubleshooting 741
3. To power off the system by using the CLI, use the command that is shown in
Example 12-5. Ensure that all FlashCopy, Metro Mirror, Global Mirror, data migration
operations, and forced deletions are stopped or allowed to complete before you continue.
Example 12-5 Powering off the system by using the CLI
>svctask stopsystem
Are you sure that you want to continue with the shut down? (y/yes to confirm)
4. Wait for the power LED on the node canisters to blink slowly, which indicates that the
power off operation completed.
12.10.2 Shutting down and starting up the infrastructure
To shut down an entire infrastructure (storage, servers, and applications), complete the
following steps:
1. Power off your servers and all applications.
2. Power off your IBM Storwize V5000 Gen2 system by using either the GUI or the CLI.
3. Remove the power cords that are connected to both power supplies in the rear of the
enclosure on every control and expansion enclosure.
4. Power off your storage area network (SAN) switches.
To start an entire infrastructure, complete the following steps:
1. Power on your SAN switches and wait until the boot completes.
2. Power on any expansion enclosures by connecting the power cord to both power supplies
in the rear of the enclosure or by turning on the power circuit.
3. Power on the control enclosures by connecting the power cords to both power supplies in
the rear of the enclosure and by turning on the power circuits.
The system starts. The system starts successfully when the status LEDs of all node
canisters in the control enclosure are permanently on, which takes no longer than 10
minutes.
Power on your servers and start all applications.
Note: When you power off an IBM Storwize V5000 Gen2, it does not automatically
restart. You must manually restart the system by removing and reapplying the power /
power cords.

Table of Contents

Other manuals for IBM Storwize V5020

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBM Storwize V5020 and is the answer not in the manual?

IBM Storwize V5020 Specifications

General IconGeneral
BrandIBM
ModelStorwize V5020
CategoryStorage
LanguageEnglish

Related product manuals