Routine Maintenance
Prepare the Machine for Maintenance
117 117
9811-3400-4
Stow the Maintenance Strut
1 Make sure the park brake is engaged and the
transmission is in neutral.
2 Install the battery isolation key. Refer to Battery
Isolator Switch.
3 Start the engine.
4 Lift the loader arm sufficiently to remove the weight
from the maintenance strut A.
5 Stop the engine.
6 Remove the strap B.
7 Remove the maintenance strut.
8 Put the maintenance strut in its stowage position
9 Remove the articulation lock. Refer to Articulation
Lock (Operation Section).
10 Remove the chocks.
S270300-V1
Fig 65.