KCP Heavy Industries Co., Ltd. Maintenance
7-7
Note ___________________________________________________________________
KCP Heavy Industries Co., Ltd. accepts no liability for damage caused by mixing oil of
different producers.
The proportion of residual oil shall not be greater than 2% after an oil change. This means
that a flushing filling with the full quantity of the new oil must be carried out. In addition, for
reasons of gasket compatibility, an oil change shall be carried out no later than 6 months
after commissioning of the machine. It should also be noted, at this point, that all
filters must be changed after 50 hours of operation, since any deposits may be
dissolved and transported to the filters by the new fluid.
_________________________________________________________________
7.4 Visual checks
This maintenance describes visual checks that you must carry out before commencing any
maintenance. You will find the service intervals in the maintenance summary at the start of this
chapter.
Danger _________________________________________________________________
Inspect the electrical cables particularly closely and carefully. There is a danger of over
voltages from defective cables, particularly when there is high air or ambient humidity.
There is a danger of fire and explosion through the formation of sparks when the machine
is used in a potentially explosive atmosphere.
_______________________________________________________________________
7.4.1 General
The general visual inspections listed below should always be carried out before any maintenance,
and each time before starting work with the machine.
► Check the fill levels of the functional fluids.
► Check that all safety equipment is available and in a fully functioning condition.