5.4 Install the Charging Station
CAUTION
Make sure there is 3 m (9.8 ft) clear space on the left side of the charging
station and 1.5 m (4.9 ft) clear space on the right side.
The charging station can be installed
on the wall
on an (optional) floor column.
5.4.1 Install a Floor Column
Note:
Do not install a floor column if installation of the charging station on a wall is
possible.
Parts
1× Floor column
8× Bolt M10 and washer (not supplied).
Installation
1. Install the floor column (1, fig. 25, page 5-4) on the barn floor with
concrete anchors (3), eight M10 bolts (5) and washers (4).
2. Make sure the floor column is level.
Figure 25. Install the floor column