Step 6. Slightly pull the LOM package forward, and lift it up at an angle as shown to remove it from the
server.
Figure 136. LOM package removal
Note: Wireless enabled LOM package and 10G SFP+ LOM package are removed with the same
method.
Step 7. Remove the eight screws that secure the system board.
Figure 137. System board removal
Step 8. Pull the system board forward and lift it up slightly to remove it from the guide pins.
Chapter 3. Hardware replacement procedures 127