Chapter 5: WebPAM
95
4. Select the physical drive you want to rebuild.
Available drives have a black frame. Selected drives have a red frame.
5. Click the Enable option.
6. From the dropdown menus, select a start time.
Start time is based on a 24-hour clock.
7. Click the Start At field to display a popup calendar.
8. Click the start date in the calendar or enter a date manually.
9. Click the Schedule button.
Cancelling a Schedule
To cancel the scheduled Rebuild:
1. Click the Logical Drive View icon in Tree View.
2. Click the Logical Drive icon.
3. Click the Rebuild tab in Management View.
4. Click the Disable option.