Maintenance 6
Annual maintenance
Annual maintenance
Work that must also be carried out
– Carry out maintenance work as neces-
sary, see ⇒ Chapter "Maintenance as re-
quired", P. 116.
– Carry out 500-hour maintenance, see
⇒ Chapter "Maintenance every 500
hours", P. 123.
Insulation resistance check (earth-
ing)
The insulation of industrial trucks should have
sufficient insulation resistance. Test the truck
and battery separately.
Testing the insulation resistance of the
electrical system
Have the insulation re
sistance of all active
electrical compone
nts checked in accordance
with DIN 57117 and DI
N 43539, VDE 0117
and VDE 0520.
Measurement voltage > nominal voltage <
500 V. Insulation is considered correct when
it is measured in relation to the chassis and is
higher than 1000 ohm/V of nominal voltage.
Please contact your Service for this test.