wc_tx002070gb.fm
128
Burner Setup—Gas E 3000
7.7 Checking and Adjusting the Air Damper (Gate) Setting
Requirements
Machine shut down
Burner cool
Procedure
Follow the procedure below to check the air damper setting.
Note: This procedure must be performed at each new job site. The proper setting
depends on environmental conditions at the job site.
1. Shut down the machine and allow it to cool.
2. Remove the burner cover.
3. Loosen the two screws (a) that secure the air adjustment plate (b).
4. Rotate the air adjustment plate so that the proper number on the air adjustment
plate lines up with the setting indicator (c). See topic Factory Settings.
5. Once the air adjustment plate is set, tighten the two screws (a).
Result
The air damper setting has now been adjusted.
b
c
a
wcghi_gr005205

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson E3000 and is the answer not in the manual?

Wacker Neuson E3000 Specifications

General IconGeneral
Electrical Requirements230 V, 50 Hz
Voltage230 V
Operating Voltage230 V
Heat Capacity3000 W
Fuel Consumption0.3 l/h
Tank Capacity12 l
Fuel Tank Capacity12 l
Heating Capacity3000 W
Fuel Consumption (l/h)0.3 l/h
Tank Capacity (l)12 l
Power Consumption3 kW

Related product manuals