EasyManuals Logo

Wacker Neuson E3000 User Manual

Wacker Neuson E3000
214 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #62 background imageLoading...
Page #62 background image
wc_tx001951gb.fm
62
Operation E 3000
Continued from the previous page.
4. Move the left pump ON-OFF switch (d) to the ON position.
5. Check the pump pressure gauge (e). The following should occur:
During the first minute of operation, the pressure should build to as high as
170 psi.
NOTICE: If the HTF reaches 170 psi (11.7 bar) after only a second or two of
operation, there is a problem. Shut down the machine and rectify the problem
before continuing.
Once flow is established, pressure should be: 125–140 psi (8.6–9.6 bar).
When the HTF is warm, operating pressure should be: 90–110 psi (6.2–7.6
bar).
6. Check the HTF flow indicator (f). The flow indicator should be spinning. If it is
not, there is a problem. Shut down the machine and rectify the problem before
continuing.
7. Repeat steps 4–6 for the right pump.
Result
HTF is now flowing.
4.21 Setting the Operating Temperature
Operating
temperature
Once the HTF is preheated, set the temperature controller to the operating
temperature. Use the chart below as a guide.
75
180
Operation type Recommended Temperature Setting
Ground thawing
80°C (180°F)
Concrete curing
7°C (20°F) above the desired temperature of the con-
crete
Air heating
80°C (180°F)

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson E3000 and is the answer not in the manual?

Wacker Neuson E3000 Specifications

General IconGeneral
Electrical Requirements230 V, 50 Hz
Voltage230 V
Operating Voltage230 V
Heat Capacity3000 W
Fuel Consumption0.3 l/h
Tank Capacity12 l
Fuel Tank Capacity12 l
Heating Capacity3000 W
Fuel Consumption (l/h)0.3 l/h
Tank Capacity (l)12 l
Power Consumption3 kW

Related product manuals