E 3000 Operation
4.8 Preparing the Machine for First Use
Preparing for
first use
To prepare your machine for first use:
1. Make sure all loose packaging materials have been removed from the machine.
2. Check the machine and its components for damage. If there is visible damage,
do not operate the machine! Contact your Wacker Neuson dealer immediately
for assistance.
3. Take inventory of all items included with the machine and verify that all loose
components and fasteners are accounted for.
4. Attach component parts not already attached.
5. Add fluids as needed and applicable, including fuel, engine oil, and battery acid.
6. Move the machine to its operating location.
4.9 Breaking in the Genset
Background
New gensets require a break-in period for the engine. If you are the first owner of
this machine, or the genset’s engine has just been rebuilt, break in the engine as
stated below.
Procedure
1. Check that the engine oil level is correct. Check that the engine oil viscosity is
appropriate for the temperature conditions. Change the oil if it is not appropriate
for the temperature conditions.
2. Operate the genset at approximately 1/2 rated power for the first two hours.
3. Operate the genset at approximately 3/4 rated power for two more hours.
4. Check the engine oil level every four hours (or twice daily) during the first 24
hours of operation.
5. Change the engine oil and filter after the first 50 hours of operation.