PROCEDURE
1 Set the cylinder lubricating feed rate for the applicable cylinders in the control system to
1.2 g/kWh.
2 Operate the engine for 24 hours.
3 Inspect the components for damage.
4 If damage occurs, find the cause and repair the fault.
5 If it is necessary to replace parts of the piston running system, do Step 2 and Step 3 again.
6 Set the feed rate to 1.1 g/kWh.
7 Operate the engine for 24 hours.
8 Set the feed rate to 1.0 g/kWh.
9 Operate the engine for 24 hours.
10 Inspect the components for damage.
11 If damage occurs, find the cause and repair the fault.
12 If it is necessary to replace parts of the piston running system, start with Step 1 again.
13 Set the feed rate to 0.9 g/kWh.
CLOSE UP
After 72 hours set the feed rate to the usual settings. Refer to the document “Lubricants” on
the WinGD website (https://www.wingd.com/) or to section [section not applicable for this
engine]
X72-B
AA00-0000-00AAA-950A-A
Operation Manual Running-in of new components
Winterthur Gas & Diesel Ltd.
- 383 - Issue 003 2021-12