112 Operating instruction SCK Gas Sampling System OI/SCK-EN Rev. E
Overview: Start-up
Proceed as follows to start up the gas sampling system:
Step Procedure Instructions in ...
1
Check installation for proper
condition.
Installation check
on
page 113
2
Fill cooling water and check
water-tightness of the cooling-
water circuit.
Preparing the cooling-
water circuit
on page 114
3
Check enclosed compressed-air
supply, fill oiler.
Preparing the com-
pressed-air supply
on
page 116
4
Switch on the gas sampling
system.
Activation
on page 118
5
After switching on: vent cool-
ing-water circuit.
After switching on: Work-
ing on the cooling mod-
ule
on page 121
6
Check pneumatic system with
the aid of the compressed-air
switch in the pneumatic box.
Checking the pneumatic
system
on page 123
7
In the control cabinet: check
frequency converter settings
and correct if necessary.
Checking frequency
converter settings
on
page 124
8
Check operating parameters of
the gas sampling system and
correct if necessary.
Checking/correcting
operating parameters
on
page 126
9
Only if using probe H:
check current monitoring
relay settings.
Check probe heating power
supply.
Checks to perform when
using probe H
on page
127
10
Insert the probe for the first
time, then adjust the speed of
the probe during operation,
adjust oil delivery rate on the
compressed-air oiler, and check
direction of rotation of the heat
exchanger.
Inserting the probe and
switching to automatic
mode
on page 130
Instructions