98 Operating instruction SCK Gas Sampling System OI/SCK-EN Rev. E
Step
Procedure
2
Suspend probe retractor on transport lugs (see photo)
using suitable lifting gear.
Note: Pay particular attention to suitable fastening
points of the lifting equipment. Observe relevant local
regulations.
3
Lift probe retractor so far that you can remove the two
mounted transport supports.
Note: Store the transport supports for any future
transport.
4
Position probe retractor in the designated position and
install appropriate support.
5
Connect the fastening elements of the probe retractor
and the system. There are 6 fastening straps on the
probe retractor for this purpose (see Figure). Maximum
load per suspension point is 10,000 N; ensure even load-
ing of the fastening elements.
CAUTION! The screw-in transport lugs are for transport-
ing the probe retractor only but not for permanent sus-
pension. For permanent suspension of the probe re-
tractor, only use the 6 designated fastening straps.
6
Remove dummy flange on wall tube.
WARNING! Risk of burning due to jet flames and hot
gases at the uncovered duct opening when the rotary
kiln is in operation. Wear a face mask against heat,
heat-proof gloves and protective welder's clothing and
respiratory protection against toxic gases.
7
Flange the mounting flange of the probe retractor on
the kiln wall tube.
8
Remove lifting gear and support material.
9
Check whether probe retractor is fastened stably
enough and adjusted to local conditions.
During assembly it may be necessary to move the probe retractor without
with compressed-air supply or control cabinet. However, this should be lim-
ited to absolutely necessary cases. Proceed as follows:
Moving the probe
during assembly