13. UNIT PREPARATION
13.01. Outdoor Unit - Interconnecting Pipes Installation
A
B
Removal Order:
Pull-Out
Pull-Down to remove
Access Panel-Electrical
A
B
B
1. Remove Access Panel-Electrical
• Remove mounting screws (4 pcs).
• Remove Access Panel-Electrical as shown in the above
illustration.
2. Remove Access Panel-Compressor
• Remove mounting screws (4 pcs).
• Remove Access Panel-Compressor as shown in the above
illustration.
3. Remove Access Panel-Piping
• Remove mounting screws (6 pcs).
• Remove Access Panel-Piping as shown in the above illustration.
• Remove all Foil Faced PE protection from pipes.
4. Install Interconnecting Pipes
• Solder refrigeration piping. Refer to piping sections for
details of field pipe sizes and piping installation procedure.