476 9424200994 Rev N
Setting
Value
BESTCOMSPlus Screen
Description
CT 2 Connection
WYE
System Parameters, Sensing
Transformers
Sets the CT 2 connection
to WYE
Phase VT Ratio
1
System Parameters, Sensing
Transformers
Sets phase VT ratio to 1
Phase VT
Connection
4W-Y
System Parameters, Sensing
Transformers
Sets phase VT connection
to 4W-Y
27/59 Mode
PN
System Parameters, Sensing
Transformers
Sets 27/59 mode to phase-
neutral
Circuit 1
Transformer
Connection
WYE
System Parameters, Transformer
Setup
Configures the primary side
for a WYE connection
Circuit 1 Ground
Compensation
No
System Parameters, Transformer
Setup
Disables the primary
winding zero sequence trap
(Optional) Circuit
1 Diff. Circuit
Primary
System Parameters, Transformer
Setup
Establishes circuit 1 on the
primary side of the
transformer. For report
labeling purposes only.
Circuit 1 Polarity
Normal
System Parameters, Transformer
Setup
Sets the phase rotation of
circuit 1 for ABC
Circuit 1 Phase
Relationship
A
System Parameters, Transformer
Setup
Sets A-phase in circuit 1
equal to the phase
relationship setting for
circuit 2
Circuit 2
Transformer
Connection
WYE
System Parameters, Transformer
Setup
Configures the secondary
side for a WYE connection
Circuit 2 Ground
Compensation
No
System Parameters, Transformer
Setup
Disables the secondary
winding zero sequence trap
(Optional) Circuit
2 Diff. Circuit
Secondary
System Parameters, Transformer
Setup
Establishes circuit 2 on the
secondary side of the
transformer. For report
labeling purposes only.
Circuit 2 Polarity
Normal
System Parameters, Transformer
Setup
Sets the phase rotation of
circuit 2 for ABC
Circuit 2 Phase
Relationship
A
System Parameters, Transformer
Setup
Sets A-phase in circuit 2
equal to the phase
relationship setting for
circuit 1
(Optional) IEC
Setup Winding 1
Wye
Primary
System Parameters, Transformer
Setup, IEC Transformer Setup
Configures the primary side
for a WYE connection
(Optional) IEC
Setup Winding 2
y0
Secondary
System Parameters, Transformer
Setup, IEC Transformer Setup
Configures the secondary
side for a WYE connection
with normal ABC phase
rotation
Circuit 1 Tap
2.00
System Parameters, Transformer
Setup
Sets the tap for circuit 1 to
2.00 A secondary
Circuit 2 Tap
2.00
System Parameters, Transformer
Setup
Sets the tap for circuit 2 to
2.00 A secondary
Phase Current Differential (87) Test BE1-11g

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Basler BE1-11g and is the answer not in the manual?

Basler BE1-11g Specifications

General IconGeneral
BrandBasler
ModelBE1-11g
CategoryRelays
LanguageEnglish

Related product manuals