6-1
6200 Packet-Optical Platform Installation, Commissioning, and Testing Procedures
Release 1.1 009-6200-201 Draft Issue 1
Copyright
©
2014 Ciena
®
Corporation September 2014
Nodal commissioning 6-
This chapter provides the commissioning procedures you must perform on a
newly installed network element. Nodal commissioning is performed using the
web user interface by entering the commissioning data of the network
element.
Procedure list
Table 6-1 lists the procedure to prepare a network element for commissioning.
Table 6-2 lists the procedures in sequence, to commission a network element.
Table 6-1
Preparing a network element for commissioning
Action Details
Connecting the PC to the local craft terminal of the
6200 network element
Procedure 6-1
Note: The commissioning data record form is used to record the commissioning
data for a network element. Refer to Chapter 12, Recording data and test results.
Table 6-2
Commissioning procedures
Step Action Details
1 Connecting the PC to the local craft terminal of the
6200 network element
Procedure 6-1
2 Logging into an uncommissioned 6200 network
element
Procedure 6-2
3 Network element initialization Procedure 6-3
4 Verifying the serial numbers of the 6200 chassis
and the circuit packs
Procedure 6-4
5 Setting the 6200 date and time Procedure 6-5

Table of Contents