System testing 7-23
6200 Packet-Optical Platform Installation, Commissioning, and Testing Procedures
Release 1.1 009-6200-201 Draft Issue 1
Copyright
©
2014 Ciena
®
Corporation September 2014
Procedure 7-5 (continued)
Testing STM-1/4/16/64/OC-3/12/48/192 protection switching with traffic on 4xFE interfaces of 6G
PKT SW circuit pack
Action
Step Action
1 Connect the test equipment, the 6200 near and far 6200 network elements as
shown in Figure 7-5 on page 7-27.
2 Determine the type of protection required.
If Then
1+1 MSP/APS is required Provision 1+1 MSP/APS group on
the optical port, both at the near and
far end network elements.
go to step 3 on page 7-24.
SNCP/UPSR is
required
Provision SNCP/UPSR on the optical
port, both at the near and far end
network elements.
go to step 3 on page 7-24.