DANGER:
Disconnect the inverter from the AC grid and PV modules before
removing covers or opening the equipment. Wait at least 5 minutes
after disconnecting from the DC and AC sources before servicing or
maintaining the inverter. Ensure hazardous high voltage and energy
inside the inverter has been discharged prior to servicing.
NOTICE:
The inverters are designed to only interconnect with an AC power
source as part of the public electric utility grid. Do not connect the AC
output of the inverters directly to any private electric utility power
equipment. The inverters are to be installed with floating or
ungrounded PV arrays only.
CAUTION:
CPS SCA50KTL-DO/US-480 and SCA60KTL-DO/US-480 inverters
weigh approximately 56kg (123.5 pounds). The wirebox portion
weighs approximately 15kg (33 pounds).
Ensure the mounting bracket is properly installed before hanging the
inverter and wirebox on the bracket. A team of two is recommended to
lift and place the inverter and wirebox into position.
INSTRUCTION:
Please check with your local electric utility supply company before
selecting a grid standard. If the inverter is operated with an incorrect
grid standard, the electric utility supply company may cancel the
interconnection agreement.
Placing the inverter into operation before the overall system complies
with the national codes, rules and safety regulations of the application
is also not permitted.