76
2. Grid Connection Rule.
Multiple grid standards are available.
Press and to select the corresponding grid standard
required for the installation and press the
ENT
key
.
INSTRUCTION:
Please check with your local electric utility supply company before
selecting a grid standard. If the inverter is operated with an incorrect
grid standard, the electric utility supply company may cancel the
interconnection agreement.
Placing the inverter into operation before the overall system complies
with the national codes, rules and safety regulations of the
application is also not permitted.