11.1.2 Charge First Mode
The order of priority for solar power usage will be Battery>Load>Grid. During the charge first period,
loads are first supplied power from the grid. If there is excess solar power after charging batteries, the
excess solar will power the loads along with grid power.
Application Scenarios
When users want solar power to charge batteries and the grid is used to power loads.
Related Settings:
Example
Solar power will be used to charge the
battery first. If there is extra power, it will be
used to take the load.

Table of Contents

Other manuals for EG4 18KPV

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the EG4 18KPV and is the answer not in the manual?

EG4 18KPV Specifications

General IconGeneral
ModelEG4 18KPV
CategoryInverter
Rated Power18 kW
Max. AC Output Current75A
Surge Power36 kW
Number of MPPTs2
Frequency50/60 Hz
Operating Temperature-25°C to 60°C
Warranty5 years
Output Voltage120/240VAC
CommunicationRS485
CoolingFan
Weight77 lbs (35 kg)
Dimensions670 x 530 x 220 mm