Installation Instructions
9.12.10 Panda_5000i_PMS_eng.R01 - Kapitel/Chapter 5: Installation Instructions Seite/Page 77
Fig. 5.9-1: Electrical installation - example
5.9.1 Installation PMGi inverter - See separat PMGi 5000 inverter manual
All electrical safety installations have to be made on board.
5.9.2 Power source selector
A power source selector switch must be installed between the generator (or if applicable, AC-Control box)
and the ship's electrical supply system. This switch must used to ensure that all AC consumers can be swit-
ched off at once. This switch should also be installed to keep the generator and shore (grid) power systems
1
2
3
4
5
1. Generator
2. Electrical fuel pump DC
3. PMGi 5000 inverter
4. iControl panel
5. Starter battery DC