5.13. Filling Commands DI, SC, AC, GD, DT, PD1 to PD21, TR
Note: All setups should be stored with the ‘SDDcommand before power-off. The filling process is
controlled by the dosing parameters. The parameters are related to the sections shown in the filling
cycle.
Phases:
1) Waiting for Start Trigger (Digital Input 1).
2) Zero Check Averaging.
3) Trigger 2 (Digital Input 2 or F/W Trigger) Starts Tare Delay.
4) Tare Weight Averaging.
5) First Pre-fill.
6) Second Pre-fill.
7) Delay after Pre-fill.
8) Coarse Filling.
9) Blanking Time after Coarse Fill.
10) Fine Filling.
11) In-flight Delay.
12) Dosed Weight Averaging.
13) Post-Filling.
14) Bottle Off. Filling Sequence Complete.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Flintec EM100-C and is the answer not in the manual?

Flintec EM100-C Specifications

General IconGeneral
BrandFlintec
ModelEM100-C
CategoryControl Unit
LanguageEnglish

Related product manuals