CHAPTER 3
Small Configuration
Installing the 19-Inch (SFD5) DCM Shelf
FNC-7500-0061-200
Issue 1, May 2009
FLASHWAVE 7500 Release 6.1
Equipment Installation
3-60
Fujitsu and Fujitsu Customer Use Only
6 Using four pan-head Phillips M4 screws (8 mm long) on each side, secure the left and right
shelf flanges to the SFD5 shelf as shown in Figure 3-41 [p. 3-57].
Figure 3-45 [p. 3-60] shows a right-side view of the SFD5 shelf after the flange is mounted.
7 Proceed to Step 12 [p. 3-61].
8 Get the flange kit for 23-inch rack mounting. Table 3-5 [p. 3-56] lists the flange kit part
numbers.
9 Identify the left and right shelf flanges. See Figure 3-42 [p. 3-57].
10 Identify the flange mounting holes for 23-Inch rack installation on the side of the SFD5 shelf.
See Figure 3-46 [p. 3-60].
11 Using four pan-head Phillips M4 screws (8 mm long) on each side, secure the left and right
shelf flanges to the SF5 shelf as shown in Figure 3-42 [p. 3-57].
Figure 3-45: Flange Mounted on Right Side of SFD5 Shelf (19-Inch Rack Installation)
Figure 3-46: Flange Mounting Holes on Right Side of SFD5 Shelf (23-Inch Rack Installation)