EasyManua.ls Logo

Fujitsu FLASHWAVE 7500 - Page 253

Fujitsu FLASHWAVE 7500
392 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
CHAPTER 4
ETSI Configuration
Installing the ETSI DCM (SFD6) Shelf
4-35
FLASHWAVE 7500 Release 6.1
Equipment Installation
Fujitsu and Fujitsu Customer Use Only
FNC-7500-0061-200
Issue 1, May 2009
Figure 4-18 [p. 4-35] shows a right-side view of the SFD6 shelf after the flange is mounted.
6 Install the SFD6 shelf in the rack directly above the heat baffle. Secure the shelf to the rack
using three rack mounting screws on each side of the shelf.
Note: If hole alignment does not permit three screws on each side, it is acceptable to secure the shelf
with only two screws on each side.
7 Install the DCM units using the following steps:
a. Locate the appropriate units to be installed and remove them from their protective ESD
packaging.
b. Loosen the thumbscrews and remove the faceplate/cover from the shelf.
c. Carefully slide each DCM unit into the appropriate shelf slot.
d. Replace the cover and tighten the thumbscrews to secure each unit in the shelf.
This procedure is complete.
Figure 4-18: Flange Mounted on Right Side of SFD6 Shelf (ETSI Rack Installation)
m1718qb_1
Revision 1, June 2009

Table of Contents

Related product manuals