CHAPTER 4
ETSI Configuration
Installing the ETSI DCM (SFD6) Shelf
FNC-7500-0061-200
Issue 1, May 2009
FLASHWAVE 7500 Release 6.1
Equipment Installation
4-34
Fujitsu and Fujitsu Customer Use Only
4 Identify the flange mounting holes for ETSI rack installation on the side of the SFD6 shelf.
See Figure 4-17 [p. 4-34].
5 Using four pan-head Phillips M4 screws (8 mm long) on each side, secure the left and right
shelf flanges to the SFD6 shelf as shown in Figure 4-15 [p. 4-32].
Figure 4-17: Flange Mounting Holes on Right Side of SFD6 Shelf (ETSI Rack Installation)