CHAPTER 4
ETSI Configuration
Installing the ETSI LAM/DCM Shelf (SDL1)
FNC-7500-0061-200
Issue 1, May 2009
FLASHWAVE 7500 Release 6.1
Equipment Installation
4-40
Fujitsu and Fujitsu Customer Use Only
Figure 4-23 [p. 4-40] shows a right-side view of the SDL1 shelf after the flange is mounted.
6 Install the SDL1 shelf in the rack directly above the heat baffle. Secure the shelf to the rack
using three rack mounting screws on each side of the shelf.
Note: If hole alignment does not permit three screws on each side, it is acceptable to secure the shelf
with only two screws on each side.
7 If the shelf came without the DCM units already installed:
a. Locate the appropriate units to be installed and remove them from their protective ESD
packaging.
b. Loosen the thumbscrews and remove the faceplate/cover from the shelf.
Figure 4-23: Flange Mounted on Right Side of SDL1 Shelf (ETSI Rack Installation)