In the Process Picture:2
Click on the Injection valve and select System pump waste.
Result: The Injection valve switches to waste position. This is necessary to achieve a
low back pressure during the purge procedure.
In the Process Picture:3
Click on the pumps.
Set Conc % B to 100% B.
Click Set % B.
Result: Only System pump B is active.