DIRECTION 5750007-1EN, REV. 1 LOGIQ E10 BASIC SERVICE MANUAL
8 - 98 Section 8-7 - Replacing Top Console Parts
Functional Checks
Perform the following functional checks to confirm the system is operational before returning the system
to the customer.
Table 8-109 Main Monitor Arm assembly replacement Functional Checks
See
Section
Functional Check Debrief Script
4-2-3 Power ON/Boot Up
LOGIQ E10 Basic Service Manual, Direction
5750007-1EN, Rev. 1. Leakage Current
measured at (record the value) and meets
allowable limits. Equipment passed all required
checks and is ready for use.
4-2-5 Main Monitor Positions and Lock
4-2-5 Operator I/O Movement - Main Monitor
4-2-7 B-Mode Checks
4-2-7 System CFM and PWD Checks
10-7-4 Grounding continuity
10-7-5 Chassis leakage current test
4-2-4 Power SHUT DOWN