GE DRAFT VOLUSON™ P8 / VOLUSON™ P6
DIRECTION 5723243, R
EVISION 6 DRAFT (MAY 23, 2018) BASIC SERVICE MANUAL
Chapter 8 - Replacement Procedures 8-129
8-41-4 Removal Procedure
1.) Draw the DPS out of the Nest Frame.
8-41-5 Installation Procedure
1.) Install the new parts in the reverse order of removal.
2.) Perform: FRU8-28: Replacement of the DPS/DPS with Battery - Functional Tests.
Figure 8-187 DPS