2. Pull out the server along the guide rails away from the cabinet. See (2) in Figure 3-31.
3. Place the removed server on an ESD platform.
Step 5 Loosen the screws that secure a guide rail. See Figure 3-32.
Figure 3-32 Removing an L-shaped guide rail
Step 6 Remove the other guide rail on the opposite side in the same way.
----End
3.6.2 Removing a Server and Adjustable Guide Rail
Step 1 Wear an ESD wrist strap or ESD gloves. For details, see 1 Safety Instructions.
Step 2 Power off the server. For details, see 4 Powering On and Off the Server.
Step 3 Disconnect all power cables and signal cables from the server.
NOTE
Remove power cables first to prevent damage or injury caused by static electricity.
Step 4 Remove the server.
1. Loosen the captive screws on the server panel using a screwdriver. See (1) in Figure
3-33.
5288 V3 Server
User Guide
3 Installing and Removing the 5288 V3
Issue 26 (2018-11-19) Copyright © Huawei Technologies Co., Ltd. 82