Huawei FusionModule2000 - Replacing a Smart U Space Manager (Connected to a UIM20 A Expansion Module)

Huawei FusionModule2000
144 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Figure 5-85 Positions of the eLight actuator and power supply (inside the
aisle)
(1) eLight actuator (2) eLight power supply
(3) Upstream fuse
Procedure
Step 1 Disconnect the upstream fuse for the eLight power supply.
Step 2 Label each cable based on the corresponding ports on the eLight power supply.
Step 3 Remove the cables from the eLight power supply.
Step 4 Remove the old eLight power supply from guide rails.
Step 5 Install the new eLight power supply in the original position and connect the
cables.
Step 6 Connect the upstream fuse for the eLight power supply.
----End
5.4.26 Replacing a Smart U Space Manager (Connected to a
UIM20A Expansion Module)
Impact on the System
The U space status of the equipment cannot be displayed during replacement.
FusionModule2000 Smart Modular Data Center
Maintenance Guide (Fusion Module Actuator) 5 Parts Replacement
Issue 01 (2020-12-25) Copyright © Huawei Technologies Co., Ltd. 130