8 Commissioning
Maschinenfabrik Reinhausen GmbH 2022 758595028/00 EN TAPCON
®
250
8.2.1 Ground test
For commissioning, carry out a ground test (check of the protective bonding
impedance) in accordance with IEC61010-1. Observe the following informa-
tion when testing:
▪ Test current: 2 times the rated current of the overcurrent protection device
in the supply line.
▪ Test duration: 1 minute for each measurement point.
▪ The measured voltage between the measurement point and the protective
conductor must be less than 10V.
To carry out the ground test, proceed as follows:
► Apply the test current at the grounding terminal of the G1 PULS DIMEN-
SION QS3.241 assembly using a constant current source and measure
the voltage between the measurement point and the protective conductor.
ð The measured voltage must remain less than 10V for a period of
1minute.
Figure54: Perform a ground test on the G1 PULS DIMENSION QS3.241 assembly
8.2.2 Performing a dielectric test
The device is tested before delivery. Note the following points if you would
like to perform a dielectric test: