RAIL KIT ASSEMBLY RAIL KIT ASSEMBLY
6-1
6.1 Rail Kit Assembly
Installing the Rack Brackets
When the server is to be installed into a rack, it is necessary to
install two rack mount brackets onto the server chassis prior to
installing the server into the rack. Follow the procedures below
to install the rack mount brackets onto the server.
Preparing for the Installation
Review all the tasks required to install and configure the
system
Review the electrical requirements and power supply input
voltage information
Examine the system’s shipping kit contents and assemble
the required tools for installation
Review ESD requirements and take safety precautions
Before installing the system into a rack, install any optional
components into the system
Stabilize the rack before installing the system, if necessary
CAUTION!
BEFORE REMOVING THE SERVER COVER, DISCONNECT ALL POWER.
U
NPLUG THE AC POWER CORD; DISCONNECT ALL PERIPHERIALS, AND
ALL LAN LINES.
!
WARNING!
Use caution when removing the inner rail from the rail kit
assembly. The rails can slide out and cause personal injury or
damage to the server.
!