Installation
128/214 Revision 06 INSTALLATION AND OPERATING INSTRUCTIONS 8DB10 864-5091.9
29 Tests
29.1 Checking the SF
6
gas filling
Checking the gas pressure Before commissioning or a rated short-duration power-frequency withstand voltage test,
the gas pressures of all gas compartments must be checked.
On all gas compartments filled at site: After having filled the gas compartments, observe a
temperature compensation time of 24 hours. Do not check the gas pressure before that
time.
Check the gas pressure in all gas compartments filled at site. If the limit values adjusted on
the indicators are underflown or exceeded, correct the gas pressure.
Leakage test 24 hours after having filled the gas compartments, check all flange connections mounted at
site and all SF
6
pipes for leaks.
For leak detection, use an SF
6
leak detector.
In case of gas leaks, these points must be disassembled and sealed again.
Checking the gas quality Check the gas quality 24 hours after filling the gas compartments.
Determine the maximum dew point with a gas hygrometer.
Dew-point temperature: -15
o
C.
Check the air content in the SF
6
gas with a gas-percentage meter.
Maximum air content: 5%.
If the gas quality is not achieved, the gas filling must be cleaned with the maintenance unit.
Monitoring the gas
pressure
After commissioning, check the gas pressures daily for a period of two weeks. If the gas
pressures drop within this period of time, please inform the Siemens representative.
After this period of time, check the gas pressures according to the maintenance instructions.
DANGER
Operation with an incorrect SF
6
gas pressure can destroy parts of the switchgear.
Do not put the switchgear into operation with too high or too low SF
6
gas pressures.