202/214 Revision 06 INSTALLATION AND OPERATING INSTRUCTIONS 8DB10 864-5091.9
43.3 Function test
Cable testing with
dismantled cable
Fig. 213: Test arrangement with dismantled cable
Earth the feeder (see page 167, "Feeder earthing").
Remove cable to be tested.
Screw test adapter tight onto cable termination of dismantled cable.
Connect test lead.
Perform voltage test.
Cable testing with
connected cable
Fig. 214: Test arrangement with connected cable
Earth the feeder (see page 167, "Feeder earthing").
Short-circuit capacitive test sockets and test sockets on integrated voltage detecting systems
(e. g. CAPDIS).
Open the circuit-breaker (see page 148, "Opening the circuit-breaker manually").
Switch three-position disconnector to OPEN position
(see page 155, "Opening the three-position disconnector manually ").
Screw test adapter onto cable termination.
Connect test lead.
Perform voltage test.
After voltage test, earth the feeder (see page 167, "Feeder earthing").