864-5091.9 • INSTALLATION AND OPERATING INSTRUCTIONS • 8DB10 • Revision 06 85/214
Installation
Preparing the busbar run for filling gas
Remove all covers with the "Filter" inscription from the housings of one busbar run.
Clean busbar housings that are dirty inside with a hand vacuum cleaner. In this case, clean
the bushing plates too with a rag.
Prepare the flanges of the busbar housings for assembly.
Clean the contact surfaces of the busbar housing covers with a lint-free paper,
and apply a thin film of grease (e.g. Polylub GLY 801, 0.40 kg).
Fig. 85: Desiccant bags in the gas compartments, design example
(position identified in the illustration by black squares; on the switchgear,
with the inscription "Filter" on the outside)
Item no. Designation Desiccant bags
Busbar housing, left end panel 2 x 250 g
Busbar housing, right end panel 2 x 250 g
Busbar housing, general type with "Filter" inscription on the cover 2 x 250 g
Top-mounted bus sectionalizer 2 x 250 g
Bus coupler 1 x 250 g
Interconnection housing of bus sectionalizer 4 x 250 g
Circuit-breaker housing, right-hand panel of bus sectionalizer
Bus riser housing
Circuit-breaker housing, general type 2 x 250 g
Three-position disconnector housing, general 2 x 250 g
NOTE
Observe the mounting location of circuit-breaker and bus riser housing in the bus sectionalizer.
If the circuit-breaker housing of a bus sectionalizer is mounted in the right-hand panel,
the bus riser housing is located in the left-hand panel.
ATTENTION
In the ambient air, the desiccant bags lose their effectiveness rapidly and cannot be used
anymore.
Use only desiccant bags whose packing is not damaged and whose humidity indicators in
the packing are blue.
➭Do not use desiccant bags if the humidity indicators are pink.
After opening the packings, mount the desiccant bags in the gas compartment within
30 minutes and close the gas compartment hermetically.