40/617
Building Technologies Division User Manual LMS14... CC1U7471en
4 Commissioning 28.01.2015
4 Commissioning
To commission the unit, follow these steps:
Prerequisite is correct mounting, correct electrical installation and, in the case of
wireless solutions, correctly working RF links to all required auxiliary units
Make all plant-specific settings. Special attention must be paid to operating page
Configuration.
For that purpose, select the relevant operating level as follows:
o Press OK on the room unit to switch to programming
o Press the Info button for at least 3 seconds and select operating level
Commissioning with the setting knob. Then, press OK
o Make the function check as described below
o Reset the attenuated outside temperature (operating page Diagnostics of
consumers, operating line Outside temp attenuated (operating page
Outside temp attenuated (8703))
Note!
The boiler manufacturer assumes responsibility for the correct parameterization
of the LMS14…, which must meet the requirements of the relevant standards
and directives
The connectors do not ensure total protection against false wiring. For this
reason, the connections must be checked prior to commissioning
Static charges must be avoided since they can damage the unit’s electronic
components when touched
Recommendation: Use ESD equipment!
To facilitate commissioning and fault tracing, the controller offers output and input tests.
When making these tests, the controller's inputs and outputs can be checked. To
perform the tests, switch to operating page Input/output test and go through all
available setting lines.
The current operating state can be checked via operating page State.
For detailed diagnostics of the plant, check operating pages Diagnostics heat source
and Diagnostics consumer.
4.1 Basic units
State of LED Meaning
LED OFF No power
LED ON Ready
Flashing Local fault
Prerequisites
Function check
Operating state
Diagnostics
Checking the LED