MN.00356.E - 003 65
Section 4.
LINE-UP
8LINE-UP OF ALFOPLUS2
8.1 GENERAL
The line-up consists of the following steps:
• switch on equipment
• alarm leds check
• connection procedure
• equipment configuration (through PC software)
• optimizing antenna orientation
• check of Ethernet connections
• quality evaluation with performance monitoring
All the parameters set on local unit must be set on remote one also. Local and remote units must be in the
same subnet.
This is a list of procedures for a fast and “basic” line-up to be performed after a correct installation.
8.2 SWITCH ON
Checks to be performed before switching on the unit are:
• check external power supply voltage.
• antenna presence - check the connection between ODU output flange and antenna.
If everything is correct, switch on the ODU.