Chapter 9: System Configuration
ThischapterdescribeshowtoconfigureyourStorEdgesystembysettingupthecommunication
betweenthesystemcomponentsandsettinguptherequiredapplication.
Configuring the RS485 Bus for Battery and Meter
Connection
ThissectiondescribeshowtosetuptheRS485communicationbetweentheinverter,meterandbattery.
Someinvertersareequippedwithabuilt-inRevenueGradeMeter(RGM),whichislocatedintheStorEdge
ConnectionUnit.Whenanadditionalmeterisinstalledfortheseinverters,thesecondmeteris
connectedtotheexistingRGMinadaisychain.
To configure the RS485 bus:
1. TurnOFForverifythattheStorEdgeConnectionUnitswitchisOFF.
2. TurntheinverterON/OFFswitchtoOFF.