2.
Tosetaminimumbatterychargelevel,sothatthebatterywillalwayshaveenergystoredincase
backuppowerisneeded,dothefollowing:
a. FromtheEnergy ManagermenuselectStorage Control.Thefollowingisdisplayed:
B a c k u p R S V D < % P V >
b. SelectBackup RSVDandsettherequiredlevelasprecentageofthebatterycapacity:
o
Forbackuppower+SmartEnergyManagement-accordingtouserrequirement
o
Forbackup-only-accordingtobatterymanufacturerrecommendation,ifprovided
Verifying StorEdge Components Functionality
Uponinstallationandconfigurationcompletion,thesystemshouldbeoperatingaccordingtothe
selectedStorEdgeapplication.
Thissectiondescribeshowtoverifythatallsystemcomponentsarefunctioningasexpected.Ifnot,refer
toTroubleshootingonpage79.
To check the inverter and meter:
1. TurntheACON.
2. Checkthemeter(installedinexportorconsumptionposition,CTarrowspointtothegrid):
a. TurntheinverterON/OFFswitchtoOFF.
b. TurnloadsONonallofthemeasuredphases.
c.
PresstheexternalLCDlightbuttontodisplaytheImportorConsumptionmeterstatusscreen,
andcheckthattheimportorconsumptionenergy(Total[Wh])isadvancing(maytakeafew
minutes,dependingontheloadssize):
I m p o r t M e t e r
S t a t u s : < O K >
< E r r o r M e s s a g e >
T o t a l [ W h ] : X X X X X X X
d. PresstheLCDlightbuttontodisplaytheExportmeterstatusscreen,andcheckthattheExport
energy(Total[Wh])isnotadvancing:(IfexportisadvancingchecktheCTsdirection.)
3. TurntheinverterON/OFFswitchtoON.
4. TurntheStorEdgeConnectionUnitswitchtoON.
5.
Whilethemodulesareexposedtosunlight(PVsystemisconnectedtothegridandtheinverteris
producingpower),presstheinverterLCDlightbuttontodisplaythepowerstatusscreen,andcheck
thatthegridACoutput(Vac)increasesto220-240V,andthetotalACoutputpowerproduced(Pac):
V a c [ V ] V d c [ V ] P a c [ W ]
2 4 0 . 7 w 3 7 1 . 9 2 3 4 9 . 3
P _ O K : X X X / Y Y Y < S _ O K >
. . . . . . . . . . . . . . . . . O N
To check Maximum Self-consumption mode:
1. TurnonasmanyloadstoensurethatconsumptionisgreaterthantheinverterACrating.
2. Ifthemeterisinstalledatthegridconnectionpointyoucancheckthattheimportenergyis
advancing(maytakeafewminutes,dependingontheloadssize):PresstheinverterLCDlightbutton
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.0
68
Verifying StorEdge Components Functionality

Table of Contents

Other manuals for SolarEdge StorEdge SE7600A-USS

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SolarEdge StorEdge SE7600A-USS and is the answer not in the manual?

SolarEdge StorEdge SE7600A-USS Specifications

General IconGeneral
BrandSolarEdge
ModelStorEdge SE7600A-USS
CategoryInverter
LanguageEnglish

Related product manuals