Chapter 8: Commissioning the Installation
Thischapterdescribeshowtoactivatethesystem,pairthepoweroptimizerstotheinverterandverify
theproperfunctioningofthesystem.
Step 1: Activating the System
1. VerifythattheinverterON/OFFswitchisOFF.
2. MovetheStorEdgeConnectionUnitON/OFFswitchtotheONposition.
WARNING!
ELECTRICAL SHOCK HAZARD. Do not touch uninsulated wires when the inverter cover is
removed.
RISQUE D’ÉLECTROCUTION, ne touchez pas les fils non isolés lorsque le couvercle de
l'onduleur est retiré.
Chapter 8: Commissioning the Installation
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.0