58
Mechanical Installation
WARNING!
• Only the qulalified personel can perform the mechanical installation following the
local standards and requirements.
• Check the existing power cables or other piping in the wall to prevent electric shock
or other damage.
CAUTION!
• Always be aware of the weight of the devices. Personal injuries may result if the
devices are lifted improperly or dropped while being transported or mounted.
• Use insulated tools and wear individual protective tools when installing the devices.
NOTICE!
• In the case of no more than 3 (including 3) battery modules in a tower, please ensure
that the bearing capacity of the supporting surface for the system must be over
940 kg.
• In the case of 4 battery modules in a tower, please ensure the bearing capacity of the
supporting surface for the system must be over 1090 kg.
• The devices must not be installed on the wood wall.
• Please ensure that the thickness of any part of the wall should not be less than
150 mm if the wall mounting is selected.
• At least two persons are required to move the devices of X3-IES system.
• Please reserve enough distance from the device to the ceiling (or the grounding) for
capacity expansion.