4. For frame R6: If you need more working space, unscrew the screw and lift the
EMC plate off. Install the EMC plate again after you have installed the motor
and input power cables.
For frame R8: Remove the EMC cover plates (4a). Remove the EMC side plates
(4b).
4 × M5
3 N·m (26 lbf·in)
4b
4b
3 × M5
3 N·m
(26 lbf·in)
5 × M5
3 N·m (26 lbf·in)
4a
4a
5. For frame R8: For easier installation, you can remove the side plates.
6 × M5
3 N·m (26 lbf·in)
6. Remove the rubber grommets of the cables to be installed from the cable entry
plate. Install the grommets downwards in unused holes.
Electrical installation North America (NEC) 123