4 HYC50 installation and commissioning
Page 49 of 102
All rights reserved. Reproduction of this document, even in part, is only permitted with the approval of alpitronic Srl.
4.4.3. Installing the mains cable in the AC grid connection box
Warning
Before you continue with the next steps, make sure that the mains cables
are completely free from voltage (see chapter 1).
Notice
The following steps must be carried out when using both the wall
mounting plate and the pedestal.
Mount the AC grid connection box with two screws (2x M4x6) in the indentation on the left
side of the wall mount plate or pedestal (see Figure 25).
Notice
Tighten the screws with a torque wrench (2.5 Nm).
Figure 25: Attach the AC grid connection box