4 HYC50 installation and commissioning
All rights reserved. Reproduction of this document, even in part, is only permitted with the approval of alpitronic Srl.
4. HYC50 installation and commissioning
This chapter describes the mechanical assembly and electrical installation of the HYC50.
Notice
The following chapter contains all essential and sufficient steps for
installing the HYC50. Additionally, an extensive step-by-step guide with
detailed photo documentation as well as two installation videos can be
found on our document platform hyperdoc.
The charging station can either be installed free-standing on a pedestal or directly on the
wall using a wall mount plate.
Warning
Observe all hazard warnings in chapter 1.
The installation, commissioning and maintenance of the charging stations
may only be carried out by people who have received professional
qualifications in accordance with the regulations applicable at the location
of the charging station and who are familiar with the local statutory safety
standards. Furthermore, these individuals must have successfully
completed the training courses prescribed by alpitronic. More information
about the mandatory training courses is available on the website
https://training.hypercharger.it/.
The warranty claim can expire if installation & commissioning are not
carried out properly.