EasyManua.ls Logo

Alpitronic hypercharger HYC50 - Table 8: Checks to be Carried out During Commissioning

Alpitronic hypercharger HYC50
102 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
HYC50 - Operation and Installation Guide
Version 2-2
Page 70 of 102
4 HYC50 installation and commissioning
All rights reserved. Reproduction of this document, even in part, is only permitted with the approval of alpitronic Srl.
All the points listed below are binding and must be carried out by the operator of the
hypercharger (or the installation company commissioned by them) at the time of
commissioning.
Depending on the individual conditions of use of the hypercharger, further checks may be
necessary. Therefore, the following list should not be taken as complete.
Commissioning checks
Description
External visual inspection
Condition of housing
IP degree of protection (IP54)
Stability
Accessibility
Checking charging cables &
plugs
Checking of all cable parts (cable sleeve, cable, cable plug,
mating face, pins) for the absence of damage (e.g. cable
sheath intact, no bruises or cracks, pins undamaged, etc.)
Are all outside cable glands tight?
Checking the screw connections
on the input terminals
Check that the screw connections on the input terminals are
tightened to 9 Nm
Checking the input mains cable
glands
Visually verify that the input mains cable glands are tight
Checking screws
Visual random check of internal screw connections
Random check of tightening torques
Check for cleanliness
Check the cleanliness inside the charging station
Check condensation
Check for the absence of traces of condensation inside the
charging station
Check filter mats
Check integrity
Review of protective measures
Visual inspection of the earthing system
Test earthing resistance
Test continuity of the equipotential bonding connections
Checks on the supply line
Check the insulation resistance at the main switch (mains
side)
Information on the existing protective device
Verification of the security
Check the insulation resistance
of DC charging outlets
Check the insulation resistance of the pins for each existing DC
charging outlet
Check RFID reader
Functional test of the RFID reader
Check connectivity of SIM cards
Check the connection to the alpitronic backend
Check the connection to the customer backend
Check the display elements
Functional test touch screen
Functional test of the screen display and, if necessary, the
touch screen of the credit card terminal
Check LED strips
Functional test of LED strips on the front door
Quality check / check of compo-
nents relevant to calibration law
(if available)
nameplate
Cabling relevant to calibration law
Adhesive seal
Detached display units relevant to calibration law
Table 8: Checks to be carried out during commissioning

Table of Contents