8 Preventive Maintenance
Page 93 of 102
All rights reserved. Reproduction of this document, even in part, is only permitted with the approval of alpitronic Srl.
8. Preventive Maintenance
For the safe operation of the charging station, annual maintenance of the charging station
and a check of its safety devices is required. Depending on the installation location of the
charging station and the environmental influences prevailing there (such as dirt, moisture,
etc.), shorter maintenance intervals may also be necessary for certain components. Regular
inspection is therefore recommended.
Warning
Observe all hazard warnings in chapter 1.
The preventive maintenance of the charging stations may only be carried
out by people who have received professional qualifications in
accordance with the regulations applicable at the location of the charging
station and who are familiar with the statutory safety standards there.
Furthermore, these individuals must have successfully completed the
training courses prescribed by alpitronic. More information about the
mandatory training courses is available on the website
https://training.hypercharger.it/.
All of the following maintenance work is mandatory.
Warranty may be void if preventative maintenance is not properly
performed.
Maintenance work
Description
External visual inspection
Condition of housing
IP degree of protection (IP54)
Stability
Accessibility
Credit card terminal (if available)
Checking charging cables & plugs
Checking of all cable parts (cable sleeve, cable, cable
connector, mating face, pins) for the absence of damage
(e.g. cable sheath intact, no bruises or cracks, pins
undamaged, etc.)
Are all outside cable glands tight?
Checking the input mains cable
glands
Visually verify that the input mains cable glands are tight
Checking screws
Visual random check of internal screw connections
Random check of tightening torques
Check for cleanliness
Check the cleanliness inside the charging station
Check condensation
Check for the absence of traces of condensation inside the
charging station